Earned Value Excel Template


(Mohamed Ahmed) #1

Overview:

This excel sheet is useful for earned value calculation in any construction project.

Earned Value Formula

Planned Value:

PV = Percent Complete (planned) x Task Budget

Earned Value:

EV = Percent Complete (actual) x Task Budget

Actual Cost:

AC = Actual Cost of the Task

Schedule Variance:

SV = EV – PV

Schedule Performance Index:

SPI = EV/PV

  • If SPI < 1, the task is behind schedule
  • If SPI = 1, the task is on schedule
  • If SPI > 1, the task is ahead of schedule

Cost Variance:

CV = EV – AC

  • If CV is negative, the task is over budget
  • If CV is zero, the project is on budget
  • If CV is positive, the project is under budget

Cost Performance Index:

CPI = EV/AC

  • If CPI < 1, the task is over budget
  • If CPI = 1, the task is on budget
  • If CPI > 1, the task is under budget

Budget At Completion:

BAC = Project Budget

Estimate At Completion:

EAC = BAC/CPI

EAC = AC + (BAC – EV)

EAC = AC + [(BAC – EV)/(SPI x CPI)]

EAC = AC + ETC

Estimate To Complete:

ETC = EAC – AC

Variance At Completion:

VAC = BAC – EAC

To Complete Performance Index:

TCPI = (BAC – EV) / (BAC – AC)

TCPI = (BAC – EV) / (EAC – AC)

التحميل
EVM Excel.zip (645.0% u)

او
https://dropfilez.com/IZr7jJ1

المصدر